Government: Planned to start construction of Long Thanh International Airport in 2021
admin 11-10-2020, 07:52

In the report on the implementation of the Long Thanh international airport project, which has just been sent by the Government to the National Assembly, the project of Long Thanh airport will be started in 2021.

Accordingly, the progress of project appraisal and approval is slow compared to the previous requirements because this is a very large and complicated project, so the International Verification Consultant (NACO – CONINCO – ARUP – AEC) completes the appraisal report inspection slower than expected (far completed). At the same time, due to the Covid -19 translation, during the verification and appraisal process, the concerned units and individuals cannot meet to discuss directly, but must do indirectly through online meeting and collecting opinions in writing so the verification and evaluation need more time.

Government: Planned to start construction of Long Thanh International Airport in 2021

Perspective of Long Thanh airport terminal. Photo: ACV

With the current progress, the Government said the project of Long Thanh international airport will start in 2021 and be completed in 2025 according to the Resolution No. 94/2015 of the National Assembly.

The Government said that on the basis of the inspection report and appraisal opinions of the State Appraisal Council members at the plenary session on May 27, Airports Corporation of Vietnam (ACV) has completed improve the project feasibility study report to submit to the State Appraisal Council. On August 24, the State Appraisal Council conducted a gathering of members’ opinions. As a result, a majority of the members agreed to approve the draft appraisal report and project content. The Ministry of Planning and Investment (the Standing Agency of the Council) has completed the appraisal report and submitted it to the Prime Minister.

Accordingly, the State Appraisal Council proposes to the Government, methods and investment plans for each component project, specifically as follows:

Component 1 project – buildings that state management agencies will assign to interdisciplinary state management agencies (Customs, Police, Border Police, Port Authorities, Medical Quarantine) capital investment implementation to ensure progress. In case the agencies are unable to allocate capital, the State management agency will select the investor in the form of PPP contract type BTL or BLT.

Project component 2 – works in service of flight management, recommended investor is the Vietnam Flight Management Corporation.

Project component 3 – essential facilities in the port, including: passenger terminal, aviation infrastructure, water supply system, wastewater treatment; No. 1 cargo terminal, garage; Traffic system connecting routes 1 and 2… will be invested by the Airports Corporation of Vietnam.

Project component 4 – service works, including the cargo terminal 2, the express cargo terminal; aviation industrial park; airport logistics area will be performed by investors, investors selected by the Ministry of Transport.

In addition, the State Appraisal Council said that the verification results, the total project investment determined by the consultant determined under Decree 32 is more than 109,200 billion VND (equivalent to more than 4.67 billion USD) down more than 2,400 billion dong (equivalent to more than 109 million USD) compared to the total initial investment. If the Decree 68 is applied, this figure is more than 109,100 billion VND (equivalent to 4.67 billion USD), a decrease of more than 2,500 billion VND (equivalent to 114.3 million USD).

The report said that the main reasons for the change in the total project investment compared to the feasibility study report submitted to the Ministry of Transport include: the estimated construction cost decreased by 2,222 billion VND, the equipment cost increased. 443 billion dong, construction investment consultation cost, project management cost, provisioning… decreased 677.9 billion dong.

It is known that the project goal is to build Long Thanh international airport to reach 4F level as decentralized by the International Civil Aviation Organization (ICAO), an important national international airport, towards is an international air hub of the region. In the first phase (2020 – 2025), the project will build 1 runway; 1 passenger terminal with synchronous auxiliary items with a capacity of 25 million passengers / year and 1.2 million tons of cargo / year.

One of the most notable architectural highlights in the phase I project is the passenger terminal with a capacity of 25 million passengers / year; includes 4 floors with a total floor area of 373,000 m3, meeting the requirements of exploitation with technology 4.0.

Currently, the Government has also directed the Ministry of Transport to request relevant agencies and units to prepare sufficient resources to implement the project as soon as the Feasibility Study Report is approved.

According to baodautu.vn, today (10/10), according to the plan, the Prime Minister will preside over the Standing Meeting of the Government on the report on the appraisal results of the feasibility study report Long Thanh international airport phase 1.

For the land clearance project invested by the People’s Committee of Dong Nai province, the government said the province committed to complete the procedure for allocating 1,810 ha of phase I priority area to the Airport Authority by the end of this year.

Previously, at the inspection of the implementation of the Long Thanh airport project on September 30, Standing Deputy Prime Minister Truong Hoa Binh asked the People’s Committee of Dong Nai Province to continue to give drastic and urgent direction to complete hand over the site on schedule as committed, ensure the completion of payment procedures and clearance of 1,810 hectares of land in priority areas for handover in October 2020; at the same time, continue to site clearance for the remaining area (within the entire 5,000 hectares of land) to disburse all the capital allocated for the project (VND 23,000 billion) in accordance with the Prime Minister’s instructions. Nguyen Xuan Phuc.

Dong Nai Provincial People’s Committee presides over and coordinates with other agencies to direct the units to have protection plans, avoid re-encroachment on the area where site clearance compensation has been completed. The Ministry of Transport and the People’s Committee of Dong Nai province have an effective solution to protect the planned construction area in phase 1 and the entire area of the planned land right after receiving and handing over the site.

In addition, the Deputy Prime Minister also assigned the Government Office to soon carry out the procedures to submit to the Prime Minister for consideration and decision to approve the feasibility study report of the project; The Ministry of Transport and agencies and units gather human resources, proactively and actively accelerate the progress of related legal procedures, fully prepare necessary conditions to strive to start projects in early quarter I / 2021.